Draw on Reserve or Default Report
Western Hills Water District Diablo Grande CFD No 1 Mello-Roos Community Facilities Districts
This report is based on unaudited information reported to the California Debt and Investment Advisory Commission pursuant to Government Code Section 53359.5(c) from sources considered to be reliable. The Commission is not liable for inadvertent errors or omissions that are reported as part of these reports.
 
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Capital Improvements
        Original Sale Date:  7/25/2014
        CDIAC Number:  2014-0945
        Type of Event:  Default
        Date of Event:  9/1/2024
        
        Amount of Default:  $3,867,139.00
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on September 1,
2024. As of the date of this notice, none of the interest or principal due on
the bonds on September 1, 2024 has been paid. Additionally, no payment
was made on September 1, 2024 for any prior interest payment date. The
amount not paid but due is the combined amount for both CDIAC Nos
2014-0945 and 2015-1143.
      
        Date Received:   9/3/2024
        
		Date posted to this website:   
        Monday, September 9, 2024
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Capital Improvements
        Original Sale Date:  6/16/2015
        CDIAC Number:  2015-1143
        Type of Event:  Default
        Date of Event:  9/1/2024
        
        Amount of Default:  $3,728,110.00
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on September 1, 2024. As
of the date of this notice, none of the interest or principal due on the bonds on
September 1, 2024 has been paid. Additionally, no payment was made on
September 1, 2024 for any prior interest payment date. The amount not paid
but due is the combined amount for both CDIAC Nos 2014-0945 and
2015-1143.
      
        Date Received:   9/3/2024
        
		Date posted to this website:   
        Monday, September 9, 2024
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Capital Improvements
        Original Sale Date:  7/25/2014
        CDIAC Number:  2014-0945
        Type of Event:  Default
        Date of Event:  3/1/2023
        
        Amount of Default:  $948,110
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on March 1, 2023. As
of the date of this notice, none of the interest due on the bonds on March 1,
2023 has been paid. On March 1, 2023, the District made a late payment of
$948,110 for interest that was originally due on September 1, 2022. The
amount not paid but due is the combined amount for both CDIAC Nos
2014-0945 and 2015-1143.
      
        Date Received:   3/29/2023
        
		Date posted to this website:   
        Wednesday, April 12, 2023
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Capital Improvements
        Original Sale Date:  7/25/2014
        CDIAC Number:  2014-0945
        Type of Event:  Default
        Date of Event:  3/1/2021
        
        Amount of Default:  $948,110.00
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on March 1, 2021. As of
the date of this notice, the interest due on the bonds has not been paid.
The amount not paid but due is the combined amount for both CDIAC Nos
2014-0945 and 2015-1143.
      
        Date Received:   3/5/2021
        
		Date posted to this website:   
        Thursday, April 1, 2021
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Capital Improvements
        Original Sale Date:  6/16/2015
        CDIAC Number:  2015-1143
        Type of Event:  Default
        Date of Event:  3/1/2023
        
        Amount of Default:  $948,110
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on March 1, 2023. As of the
date of this notice, none of the interest due on the bonds on March 1, 2023 has
been paid. On March 1, 2023, the District made a late payment of $948,110 for
interest that was originally due on September 1, 2022.
      
        Date Received:   3/1/2021
        
		Date posted to this website:   
        Wednesday, April 12, 2023
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Capital Improvements
        Original Sale Date:  6/16/2015
        CDIAC Number:  2015-1143
        Type of Event:  Default
        Date of Event:  3/1/2021
        
        Amount of Default:  $948,110.00
        
        Contact:  Andrew Bavender, Goodwin
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on March 1, 2021. As of
the date of this notice, the interest due on the bonds has not been paid.
The amount not paid but due is the combined amount for both CDIAC Nos
2014-0945 and 2015-1143.
      
        Date Received:   3/1/2021
        
		Date posted to this website:   
        Thursday, April 1, 2021
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Capital Improvements
        Original Sale Date:  7/25/2014
        CDIAC Number:  2014-0945
        Type of Event:  Default
        Date of Event:  9/1/2020
        
        Amount Withdrawn:  $3,813,110.00
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on September 1, 2020. Additionally, there were mandatory sinking fund redemptions scheduled for the same date in the total amount of $2,865,000. As of the date of this notice, none of the interest or principal due on the bonds on September 1, 2020 has been paid. On September 1, 2020, the District made a late payment of $948,110 for interest that was originally due on March 1, 2020. 
The amount not paid but due is the combined amount for both CDIAC Nos 2014-0945 and 2015-1143.
      
        Date Received:   9/3/2020
        
		Date posted to this website:   
        Thursday, October 8, 2020
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1 
        County:  Stanislaus
        Project:  Capital Improvements
        Original Sale Date:  6/16/2015
        CDIAC Number:  2015-1143
        Type of Event:  Default
        Date of Event:  9/1/2020
        
        Amount of Default:  $3,813,110.00
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on September 1, 2020.  Additionally, there were mandatory sinking fund redemptions scheduled for the same date in the total amount of $2,865,000.  As of the date of this notice, none of the interest or principal due on the bonds on September 1, 2020 has been paid.  On September 1, 2020, the District made a late payment of $948,110 for interest that was originally due on March 1, 2020. 
The amount not paid but due is the combined amount for both CDIAC Nos 2014-0945 and 2015-1143
      
        Date Received:   9/3/2020
        
		Date posted to this website:   
        Thursday, October 8, 2020
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Water District
        Original Sale Date:  7/25/2014
        CDIAC Number:  2014-0945
        Type of Event:  Default
        Date of Event:  3/2/2020
        
        Amount of Default:  $948,110.01
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc
        Phone Number:  (916) 561-0890
        Comments:  
         A total of $948,110.01 in interest on the Bonds was due on March 2, 2020. As of the date of notice submitted on March 6, 2020, the interest due on the bonds has not been paid.  The amount not paid but due is the combined amount for both CDIAC numbers 2014-0945 & 2015-1143.
      
        Date Received:   3/11/2020
        
		Date posted to this website:   
        Wednesday, March 18, 2020
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Water District
        Original Sale Date:  6/16/2015
        CDIAC Number:  2015-1143
        Type of Event:  Default
        Date of Event:  3/2/2020
        
        Amount of Default:  $948,110.01
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110.01 in interest on the Bonds was due on March 2, 2020. As of the date of notice submitted on March 6, 2020, the interest due on the bonds has not been paid.  The amount not paid but due is the combined amount for both CDIAC numbers 2014-0945 & 2015-1143.
      
        Date Received:   3/11/2020
        
		Date posted to this website:   
        Wednesday, March 18, 2020
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  7/25/2014
        CDIAC Number:  2014-0945
        Type of Event:  Draw on Reserve
        Date of Event:  9/3/2019
        
        Amount Withdrawn:  $538,825.01
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        On September 3, 2019, a total of $538,825 was withdrawn from the Reserve Fund to partially fund the debt service payment due on the Bonds on that date. On September 13, 2019, an additional $1,618,673 was withdrawn from the Reserve Fund to partially fund the Bonds debt service payment due on September 3, 2019. Overall, the total amount drawn from the Reserve Fund was $2,157,498. The balance of the Reserve Fund following these withdrawals is $0. Reserve fund is shared between 2014-0945 and 2015-1143 The amount of the draw reported is the total amount withdrawn for both bonds.
      
        Date Received:   9/13/2019
        
		Date posted to this website:   
        Tuesday, September 17, 2019
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  7/25/2014
        CDIAC Number:  2014-0945
        Type of Event:  Default
        Date of Event:  9/3/2019
        
        Amount of Default:  $2,822,935.00
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $847,935 in interest on the Bonds was due on September 3, 2019. Additionally, there was a mandatory sinking fund redemption scheduled for the same date in the amount of $1,975,000. The interest due on the Bonds was not paid until September 13, 2019. As of the date of this notice, the principal due on the bonds has not been paid. The District anticipates that a portion of the principal due for the mandatory sinking fund redemption will be paid on Monday, September 16, 2019.
      
        Date Received:   9/13/2019
        
		Date posted to this website:   
        Tuesday, September 17, 2019
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  7/25/2014
        CDIAC Number:  2014-0945
        Type of Event:  Draw on Reserve
        Date of Event:  9/13/2019
        
        Amount Withdrawn:  $1,618,673.38
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        On September 3, 2019, a total of $538,825 was withdrawn from the Reserve Fund to partially fund the debt service payment due on the Bonds on that date. On September 13, 2019, an additional $1,618,673 was withdrawn from the Reserve Fund to partially fund the Bonds debt service payment due on September 3, 2019. Overall, the total amount drawn from the Reserve Fund was $2,157,498. The balance of the Reserve Fund following these withdrawals is $0. Reserve fund is shared between 2014-0945 and 2015-1143 The amount of the draw reported is the total amount withdrawn for both bonds.
      
        Date Received:   9/13/2019
        
		Date posted to this website:   
        Tuesday, September 17, 2019
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  6/16/2015
        CDIAC Number:  2015-1143
        Type of Event:  Draw on Reserve
        Date of Event:  9/3/2019
        
        Amount Withdrawn:  $538,825.01
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        On September 3, 2019, a total of $538,825 was withdrawn from the Reserve Fund to partially fund the debt service payment due on the Bonds on that date. On September 13, 2019, an additional $1,618,673 was withdrawn from the Reserve Fund to partially fund the Bonds debt service payment due on September 3, 2019. Overall, the total amount drawn from the Reserve Fund was $2,157,498. The balance of the Reserve Fund following these withdrawals is $0. Reserve fund is shared between 2014-0945 and 2015-1143 The amount of the draw reported is the total amount withdrawn for both bonds.
      
        Date Received:   9/13/2019
        
		Date posted to this website:   
        Tuesday, September 17, 2019
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  6/16/2015
        CDIAC Number:  2015-1143
        Type of Event:  Draw on Reserve
        Date of Event:  9/13/2019
        
        Amount Withdrawn:  $1,618,673.38
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        On September 3, 2019, a total of $538,825 was withdrawn from the Reserve Fund to partially fund the debt service payment due on the Bonds on that date. On September 13, 2019, an additional $1,618,673 was withdrawn from the Reserve Fund to partially fund the Bonds debt service payment due on September 3, 2019. Overall, the total amount drawn from the Reserve Fund was $2,157,498. The balance of the Reserve Fund following these withdrawals is $0. Reserve fund is shared between 2014-0945 and 2015-1143 The amount of the draw reported is the total amount withdrawn for both bonds.
      
        Date Received:   9/13/2019
        
		Date posted to this website:   
        Tuesday, September 17, 2019
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  6/16/2015
        CDIAC Number:  2015-1143
        Type of Event:  Draw on Reserve
        Date of Event:  3/1/2019
        
        Amount Withdrawn:  $36,516.33
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        On March 1, 2019, the District requested a draw of $36,516.33 from the Reserve Fund to fund a portion of the debt service payment due March 1, 2019. The draw was necessary due to delinquencies in payment of the special tax. The draw was necessary due to delinquencies in payment of the special tax. Approximately 62% of the special tax levy for fiscal year 2017-18 was delinquent. Reserve Fund is shared between 2014-0945 and 2015-1143 The amount of the draw reported is the total amount withdrawn for both bonds.
      
        Date Received:   3/6/2019
        
		Date posted to this website:   
        Tuesday, September 17, 2019
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  7/25/2014
        CDIAC Number:  2014-0945
        Type of Event:  Draw on Reserve
        Date of Event:  9/4/2018
        
        Amount Withdrawn:  $2,208,682.45
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        On September 4, 2018, the District requested a draw of $2,208,682.45 from the Reserve Fund to fund a portion of the debt service payment due September 4, 2018. The draw was necessary due to delinquencies in payment of the special tax. The draw on the Reserve Fund was made on September 4, 2018 and the interest and principal payments due on the Bonds were made on time.
      
        Date Received:   9/7/2018
        
		Date posted to this website:   
        Friday, December 28, 2018
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  6/16/2015
        CDIAC Number:  2015-1143
        Type of Event:  Draw on Reserve
        Date of Event:  9/4/2018
        
        Amount Withdrawn:  $2,208,682.45
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        On September 4, 2018, the District requested a draw of $2,208,682.45 from the Reserve Fund to fund a portion of the debt service payment due September 4, 2018. The draw was necessary due to delinquencies in payment of the special tax. The draw on the Reserve Fund was made on September 4, 2018 and the interest and principal payments due on the Bonds were made on time.
      
        Date Received:   9/7/2018
        
		Date posted to this website:   
        Friday, December 28, 2018
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  7/26/2001
        CDIAC Number:  2000-1743
        Type of Event:  Draw on Reserves
        Date of Event:  9/1/2008
        
        Amount Withdrawn:  $798,007.00
        
        Contact:  Marc Grijalva, Willdan Financial Services
        Phone Number:  (800) 755-6864
        Comments:  
        
      
        Date Received:   9/12/2008
        
		Date posted to this website:   
        Friday, September 12, 2008
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  12/13/2002
        CDIAC Number:  2002-1904
        Type of Event:  Draw on Reserves
        Date of Event:  9/1/2008
        
        Amount Withdrawn:  $248,471.74
        
        Contact:  Marc Grijalva, Willdan Financial Services
        Phone Number:  (800) 755-6864
        Comments:  
        
      
        Date Received:   9/12/2008
        
		Date posted to this website:   
        Friday, September 12, 2008
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  4/27/2004
        CDIAC Number:  2004-0373
        Type of Event:  Draw on Reserves
        Date of Event:  9/1/2008
        
        Amount Withdrawn:  $668,137.58
        
        Contact:  Marc Grijalva, Willdan Financial Services
        Phone Number:  (800) 755-6864
        Comments:  
        
      
        Date Received:   9/12/2008
        
		Date posted to this website:   
        Friday, September 12, 2008
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  
        Original Sale Date:  1/13/2005
        CDIAC Number:  2005-0066
        Type of Event:  Draw on Reserves
        Date of Event:  9/1/2008
        
        Amount Withdrawn:  $327,900.64
        
        Contact:  Marc Grijalva, Willdan Financial Services
        Phone Number:  (800) 755-6864
        Comments:  
        
      
        Date Received:   9/12/2008
        
		Date posted to this website:   
        Friday, September 12, 2008
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Capital Improvements
        Original Sale Date:  7/25/2014
        CDIAC Number:  2014-0945
        Type of Event:  Default
        Date of Event:  9/1/2023
        
        Amount of Default:  $3,728,110.00
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on September 1, 2023.
As of the date of this notice, none of the interest or principal due on the
bonds on September 1, 2023 has been paid. Additionally, no payment was
made on September 1, 2023 for any prior interest payment date. The
amount not paid but due is the combined amount for both CDIAC Nos
2014-0945 and 2015-1143.
      
        Date Received:   
        
		Date posted to this website:   
        Monday, November 27, 2023
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Stanislaus
        Original Sale Date:  7/25/2014
        CDIAC Number:  2014-0945
        Type of Event:  Default
        Date of Event:  9/1/2021
        
        Amount of Default:  $6,368,110.00
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on September 1,2021.
Additionally, a total of $5,420,000 in principal was scheduled to mature on
September 1, 2021. As of the date of this notice, none of the interest or principal
due on the bonds on September 1, 2021 has been paid. On September 1, 2021,
the District made a late payment of $948,110 for interest that was originally due
on March 1, 2021. The amount not paid but due is the combined amount for
both CDIAC Nos 2014-0945 and 2015-1143.
      
        Date Received:   
        
		Date posted to this website:   
        Wednesday, January 12, 2022
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Capital Improvements
        Original Sale Date:  6/16/2015
        CDIAC Number:  2015-1143
        Type of Event:  Default
        Date of Event:  9/1/2023
        
        Amount of Default:  $3,728,110.00
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on September 1, 2023. As
of the date of this notice, none of the interest or principal due on the bonds on
September 1, 2023 has been paid. Additionally, no payment was made on
September 1, 2023 for any prior interest payment date. The amount not paid
but due is the combined amount for both CDIAC Nos 2014-0945 and
2015-1143.
      
        Date Received:   
        
		Date posted to this website:   
        Monday, November 27, 2023
       
    
         	  
        Issuer:  Western Hills Water District Diablo Grande CFD No 1
        County:  Stanislaus
        Project:  Capital Improvements
        Original Sale Date:  6/16/2015
        CDIAC Number:  2015-1143
        Type of Event:  Default
        Date of Event:  9/1/2021
        
        Amount of Default:  $6,368,110.00
        
        Contact:  Andrew Bavender, Goodwin Consulting Group Inc.
        Phone Number:  (916) 561-0890
        Comments:  
        A total of $948,110 in interest on the Bonds was due on September 1,2021.
Additionally, a total of $5,420,000 in principal was scheduled to mature on
September 1, 2021. As of the date of this notice, none of the interest or principal
due on the bonds on September 1, 2021 has been paid. On September 1, 2021,
the District made a late payment of $948,110 for interest that was originally due
on March 1, 2021. The amount not paid but due is the combined amount for
both CDIAC Nos 2014-0945 and 2015-1143.
      
        Date Received:   
        
		Date posted to this website:   
        Wednesday, January 12, 2022
       